Tuesday, 29 January 2013

Gyprock is being done

We had our electrical walk through on Tuesday last week, and gyprock started on Friday. Went over to the house on Saturday and though that almost half of the house is done. SS said to allow 8 days for the gyprock to be completed though. It's getting there.. we're almost at lock up!

We noticed, unfortunately after our walk through on Tuesday, that the direction of one of the sliding door would not be practical. We raised it with SS but haven't got any update whether he can still change it. Currently the sliding door in the dining room is opening to the corner, but we should have it opening to the kitchen to keep both sides of the corner free. Cross fingers he can make this happen!
Kitchen

Dining/kitchen
The left hand stacker door is the one we hope we can change direction.

Main bedroom

The other bedroom
In the meantime, we have been searching for a new sofa for the living room, and finally bought one!!
We were tossing between white or black.. as we love the look of white sofa. It will be modern and very contemporary. But finally settled in on black sofa for the practically of having a 2-year-old.

We decided on a full grain leather sofa (the lady said it's top of the range leather). It needs to be made first so estimated delivery to the warehouse is end of April, and we have 4 weeks to get it delivered. So the timing should work well for us.

Here is the picture of the sofa.. but in black.



Monday, 24 December 2012

Before the Xmas shutdown

Went to check our place before the Xmas shutdown. Really happy on how things are progressing. We have the bricks all finished.

Have a Merry Christmas and have a great year in 2013!







Monday, 17 December 2012

We have roof!

SS called last week saying that they will start bricks on Monday, so we went on Sunday expecting some bricks done.. a bit sceptical about having the bricks and roof completed before Christmas. But we have roof already!!! And brick are about 75% done it seems?

It is just flying.. really happy with our roof and brick selections now that it's right in front of us. Wasn't quite sure about light coloured roof before.. but it looks good :)

MJH has always advertised that their roof pitch is higher than other builders and more imposing, but didn't really realised what it means until we saw our roof. It's HIGH! 

Front view

Another front view
Front door
 
Garage

You can see the Anticon blanket for insulation

The other side of the house

Tuesday, 27 November 2012

Frame completed!

We met with our SS yesterday to see the finished frame! Sooooo excited to walk in from the front door and actually walked through the house.. know where the rooms are, saw the steel frame of the bath (didn't know it needs a frame!) and even the steel frame of the built in wardrobes. It was just amazing! Really neat work, very clean and we are very happy with MJH. The windows and sliding doors are also done. A couple of windows was not yet installed because the placement wasn't correct, SS has spotted them and will get them fixed.

We didn't upgrade to higher sliding doors to the alfresco and backyard.. now regret it as they look sooooo short :( Oh well, what can you do now..





Thursday, 22 November 2012

Frame is starting

They have started with the frames, hope all goes well and it can be completed by Monday.


Monday, 19 November 2012

Slab is poured.. frames have arrived!

Our slab was poured on Monday, so didn't get a chance to visit until Saturday. We got a nice surprise that the frames have already delivered!! Can't wait to know when they will start the frames.

So off to send the bank the instruction to pay for the first progress payment...



Monday, 5 November 2012

Piering day

It was the perfect day for our piering. Met the Slab Supervisor on our block and good news was that we are well under our allowance :) 



Hope that the weather holds until around Wednesday when our slab is scheduled to be poured.