Monday, 3 June 2013

Getting there..

It's getting there.. we just finished the lighting.. and it's looking great.
Will post some more photos when I have time to clean up other parts of the house :)
Kitchen

Family room - still need to find a new entertainment unit.

Dining room - will need to lengthen the pendant light a bit.. will get to it someday :P
Second bedroom - our daughter's bedroom

Kids activities - don't think this will ever be tidy :)


Wednesday, 17 April 2013

PCI completed, handover scheduled

We had PCI on Thursday and only minor things picked up. Many paint defects, and the cupboard in the laundry hasn't been fixed. Aside from that we are quite happy with how the house turned up. Of course after just about an hour we just sort of just glanced through.. thinking it was a good idea to have Howard Ryan coming in as we have headache already :p I don't know how people can cope with 3 hours PCI, my eyes couldn't see clearly any more after one hour.

We have chased up the head office for our invoice and occupancy certificate as the bank won't release payment without it and it would hold up the final payment. We got the final occupancy certificate on time for the bank to release the payment, and the cheque is in our hands ready for handover.

Look forward to handover tomorrow.. then having a week to organise our blinds, flooring and driveway before we move in. Hopefully Telstra can be sorted out as well, I don't really want to be without internet!

Our daughter will have her orientation in her new daycare too in the morning before the handover. Hope she likes her new school and not missing her old friends and teachers too much.


Friday, 8 March 2013

It's painted and looking good :)

They have finished the first coat of paint, and have corrected the gyprock or paint defects SS found.
Our vanities have also been installed, along with the stone benchtop for the vanities and kitchen.
Next week they will do the second coat of pain, and the week after all the fit out for shower screens, mirrors, and electrical.
SS reckon it will be about 3 weeks until PCI. 

Ensuite vanity

Bed 2

Master bedroom

Main bathroom
Dining - sliding doors have been swapped :) 

Family area

Kitchen - benchtop is still covered so they won't scratch when tradies drop their tools


Friday, 22 February 2013

Getting there..

Finally we can get into the house yesterday, as SS asked us to check if the tiles for the wet areas are the correct ones. Really happy with how things are looking. 

Painters are scheduled to start Monday for the first coat.



Our kitchen! ^_^

Kitchen bench without the stone benchtop


Laundry bench

Living room and dining room


Ensuite


Monday, 11 February 2013

Lock up!

YAY!! We are in lock up! Went over on Saturday to find the carpenters working hard. Hubby went in and got scolded by one of them for going in with open toe sandals :p So couldn't get in basically.. went to Rouse Hill for lunch and groceries.. went over again but they are still working hard. oh well..

The stacker doors have been changed. Both the doors in the kitchen and dining are opening to the middle wall. We're really happy that we can change this :)

Now we need to think about fencing since the neighbours on both left and right hand side hasn't started building. The ones at the back (yes we got 4 properties as our neighbours :P) I think have been completed or very close to, but hasn't received anything from them regarding fencing.

An issue that has surfaced is with our laminate flooring. We have an agreed installation price for the laminate but didn't get anything in writing. Silly.. I know now. The sales person claimed that is they put it in the invoice it would be more expensive because the store has to take a cut and they can't do a good price. So we will have to pay directly to the installer. We have heard this from pretty much most of the stores, so we just went with it. Now that we wanted to confirm our prices and give them heads up that soon they can come and measure the house, they didn't remember ever giving us the cheap installation price. We are waiting from them, as the person I spoke to wasn't the sales person, although he was there and was part of the conversation. So we would give them the benefit of the doubt and wait to hear from them.

Thursday, 7 February 2013

Gyprock is almost done

Finally got some time to upload my pics from last weekend. Gyprock was almost done.
Got word from SS that the sliding door can be changed, but will leave a hole as they will be using the same door put re-install it upside down.. so I asked him is we can swap the kitchen sliding door and the dining one so we don't have any holes on the door. Hopefully we can do this..

Entrance hallway

Dining

Bathroom

Kitchen

Main bath - shower

Media room

Pantry

Bedroom 2

Tuesday, 29 January 2013

Gyprock is being done

We had our electrical walk through on Tuesday last week, and gyprock started on Friday. Went over to the house on Saturday and though that almost half of the house is done. SS said to allow 8 days for the gyprock to be completed though. It's getting there.. we're almost at lock up!

We noticed, unfortunately after our walk through on Tuesday, that the direction of one of the sliding door would not be practical. We raised it with SS but haven't got any update whether he can still change it. Currently the sliding door in the dining room is opening to the corner, but we should have it opening to the kitchen to keep both sides of the corner free. Cross fingers he can make this happen!
Kitchen

Dining/kitchen
The left hand stacker door is the one we hope we can change direction.

Main bedroom

The other bedroom
In the meantime, we have been searching for a new sofa for the living room, and finally bought one!!
We were tossing between white or black.. as we love the look of white sofa. It will be modern and very contemporary. But finally settled in on black sofa for the practically of having a 2-year-old.

We decided on a full grain leather sofa (the lady said it's top of the range leather). It needs to be made first so estimated delivery to the warehouse is end of April, and we have 4 weeks to get it delivered. So the timing should work well for us.

Here is the picture of the sofa.. but in black.



Monday, 24 December 2012

Before the Xmas shutdown

Went to check our place before the Xmas shutdown. Really happy on how things are progressing. We have the bricks all finished.

Have a Merry Christmas and have a great year in 2013!







Monday, 17 December 2012

We have roof!

SS called last week saying that they will start bricks on Monday, so we went on Sunday expecting some bricks done.. a bit sceptical about having the bricks and roof completed before Christmas. But we have roof already!!! And brick are about 75% done it seems?

It is just flying.. really happy with our roof and brick selections now that it's right in front of us. Wasn't quite sure about light coloured roof before.. but it looks good :)

MJH has always advertised that their roof pitch is higher than other builders and more imposing, but didn't really realised what it means until we saw our roof. It's HIGH! 

Front view

Another front view
Front door
 
Garage

You can see the Anticon blanket for insulation

The other side of the house

Tuesday, 27 November 2012

Frame completed!

We met with our SS yesterday to see the finished frame! Sooooo excited to walk in from the front door and actually walked through the house.. know where the rooms are, saw the steel frame of the bath (didn't know it needs a frame!) and even the steel frame of the built in wardrobes. It was just amazing! Really neat work, very clean and we are very happy with MJH. The windows and sliding doors are also done. A couple of windows was not yet installed because the placement wasn't correct, SS has spotted them and will get them fixed.

We didn't upgrade to higher sliding doors to the alfresco and backyard.. now regret it as they look sooooo short :( Oh well, what can you do now..





Thursday, 22 November 2012

Frame is starting

They have started with the frames, hope all goes well and it can be completed by Monday.


Monday, 19 November 2012

Slab is poured.. frames have arrived!

Our slab was poured on Monday, so didn't get a chance to visit until Saturday. We got a nice surprise that the frames have already delivered!! Can't wait to know when they will start the frames.

So off to send the bank the instruction to pay for the first progress payment...